NYSCA PS84K

Project Description
This project involved a full replacement of the school’s outdated boiler system and upgrades to building-wide heating and temperature controls. Work included removing old fuel tanks, boilers, and associated piping, and installing new high-efficiency gas-fired boilers, hot water systems, and control panels. A modern digital temperature control system was added to improve energy efficiency and indoor climate management. Additional upgrades included new sump pumps, ductwork, and piping, as well as testing and balancing of all systems.
Construction Company
Kordun
69-41 76th Street, Middle Village, NY 11379 , (718) 326-3277


Prev
Next
Project Info
Project Location
- 250 Berry Street, Brooklyn, NY, 11249
Governing Agency
- NYSCA
Project Size
- $6,230,000
Project Start
- May-2022
Estimated Project Finish
- May-2024